Home > Money > Question
Need Expert Advice?Our Gurus Can Help

Flat Possession Delayed: Can I Still Get My Compensation?

Ramalingam

Ramalingam Kalirajan  |10872 Answers  |Ask -

Mutual Funds, Financial Planning Expert - Answered on Aug 16, 2024

Ramalingam Kalirajan has over 23 years of experience in mutual funds and financial planning.
He has an MBA in finance from the University of Madras and is a certified financial planner.
He is the director and chief financial planner at Holistic Investment, a Chennai-based firm that offers financial planning and wealth management advice.... more
VINAY Question by VINAY on Apr 16, 2024Hindi
Listen
Money

i have bought a flat in June'22 i was told that possession will be given on or before 31/12/2022 and also promised that if possession not given as per schedule i.e 31/12/2022 then they will give me monthly compensation till the actual possession of flat and they have given me possession after one year and they also refused to give any compensation so please advise what to do now

Ans: Gather Evidence: Collect all documents related to the flat purchase, including the agreement, possession date promises, and any correspondence about delays or compensation.
Send a Legal Notice: Clearly outline the breach of contract, the promised compensation, and demand payment.
Consider Mediation or Arbitration: If direct negotiation fails, explore these options to resolve the dispute.
Consult a Lawyer: Seek professional advice to understand your legal rights and options, including potential litigation.
Act promptly as there might be time limitations for legal action.

Best Regards,

K. Ramalingam, MBA, CFP,

Chief Financial Planner,

www.holisticinvestment.in
DISCLAIMER: The content of this post by the expert is the personal view of the rediffGURU. Users are advised to pursue the information provided by the rediffGURU only as a source of information to be as a point of reference and to rely on their own judgement when making a decision.
Money

You may like to see similar questions and answers below

Ramalingam

Ramalingam Kalirajan  |10872 Answers  |Ask -

Mutual Funds, Financial Planning Expert - Answered on Jul 25, 2024

Asked by Anonymous - Jul 15, 2024Hindi
Money
Dear Sir We had booked a flat in one of the projects in Karnataka ( 15 + years back) but when the project is about to complete the land owner of that apartment filed the case against the builder because the builder had constructed few flats illegally in that project.. The land owner had demanded few crores from the builder for illegally constructing the flat...During that time we were in abroad and 3 flats werent registered in this project one is ours and 2 more flat owners were in abroad too..Thats out of 35 flats... Hence the builder had registered three flats in their name for the safety..But till now we havent got registered of that flat in our name becos there is case in the court. Hence there is no completion certificate issued for that project..etc.... and no flat owner can sell their flat due to the court case. However the builder had given us a power of attorney for the flat for rent it out or stay... And we have rented the flat and are getting the rent... we have been regularly followed up with the builder, he everytime promises today tomorrow....like this 15+ years passed...last year we asked for a replacement flat in one of their new project and he agreed to give us a replacement flat provided we pay some extra bucks as per the rate...We agreed for that and got the agreement signed and also got the sale deed of the land etc.. we have paid the payment in cheques.Its a huge project and completion of the project is bit slow and got delayed.... Recently, the builder had sent an email to all flat owners to register their flats but when we consulted for registration the builder said he had to transfer the payment done by us from the previous project to this new project...hence it would take time (by the way thats their internal issue) everytime we consulted for registration he says it would take one months time and his legal team is working on it...Sometime he says the court case should get over of the other project and then only he can help to register the the present flat..(though the previous flat is in their name itself) we have nothing to do with case (as the Case is between land owner and builder) also the previous flat registration al in their name..we have only agreement and receipts.of payment done...hence so far the flat is not registered...most of the flats got registered in the new project...The project is not completed yet it would take one more year... My question is why the builder is delaying the registration process of our flat and why is he not doing the internal issues solved and help us to register our flat in our name... Should we register the flat ourselves provided we get required documents from the builder? Or consult a lawyer in this regard...Pls guide...
Ans: You booked a flat 15+ years ago in Karnataka. The project faced legal issues due to illegal construction. You haven’t been able to register the flat in your name.

Builder’s Delay
The builder registered three flats, including yours, in their name. You have a power of attorney to rent it out. The builder promised a replacement flat in a new project, but the registration is still delayed.

Key Questions
Why is the builder delaying registration?
Should you register the flat yourself?
Should you consult a lawyer?
Builder's Delay Analysis
Internal Issues
Fund Transfer: The builder needs to transfer payments from the previous project to the new one. This seems to be causing delays.

Legal Complications: The builder indicates that the ongoing court case may affect the registration process. However, you have no involvement in this case.

Project Completion
Project Delay: The new project is not yet complete. This might also contribute to the registration delay.
Recommendations
Consult a Lawyer
Legal Advice: Consult a lawyer to understand your legal standing and options.

Documentation: Ensure all your documents are in order. The lawyer can help review and prepare necessary paperwork.

Registration Process
Self-Registration: With the required documents from the builder, you might register the flat yourself. This requires legal guidance.

Follow-Up: Continue to follow up with the builder regularly. Ensure all communication is documented.

Legal Action
Notice to Builder: Your lawyer may suggest sending a legal notice to the builder for delaying registration.

Court Case: If the builder doesn’t cooperate, consider filing a case against them. This might expedite the process.

Insightful Evaluation
Assessing Risks
Builder's Reliability: Evaluate the builder’s past projects and their completion rates. This helps in assessing the likelihood of further delays.

Legal Risks: Understand the legal risks associated with the ongoing court case. Your lawyer can provide a detailed assessment.

Future Steps
Replacement Flat: If the builder provides a replacement flat, ensure all legal aspects are clear before agreeing.

Backup Plan: Have a backup plan in case the registration process faces more delays. This might include exploring other housing options.

Communication
Transparent Dialogue: Maintain open and transparent communication with the builder. Document all discussions and agreements.

Legal Assistance: Have your lawyer involved in all major communications with the builder. This ensures legal backing.

Final Insights
Proactive Steps
Consulting a lawyer is crucial. They can guide you through the legal complexities and help expedite the registration process.

Keep all your documents organized. This will be helpful during any legal procedures.

Regularly follow up with the builder. Ensure you have written records of all communications.

Evaluate the reliability of the builder and the legal implications of the ongoing court case. This helps in making informed decisions.

Best Regards,

K. Ramalingam, MBA, CFP,

Chief Financial Planner,

www.holisticinvestment.in

..Read more

Ramalingam

Ramalingam Kalirajan  |10872 Answers  |Ask -

Mutual Funds, Financial Planning Expert - Answered on Sep 08, 2025

Asked by Anonymous - Sep 02, 2025Hindi
Money
RESPECTED SIR SOLD AN ANCISTOR SHOP FOR 85 LAC IN 2022 AND INVESTED THE MONEY IN BUYING A FLAT WHOSE OC AND POSSESION HAD BEEN GIVEN TO US IN 2023 BUT SOME ISSUE IS THERE BETWEEN THE DEVELOPER AND AUTHORITY AND REGISTRATION OF PROPERTY IS HANGING SINCE ALTHOUGHT BOUGHT THE STAMP PAERS ALSO , PLEASE ADVICE WHAT COULD BE THE LONG TERM REPRICUSION ON ME
Ans: It is common in India for registration delays to happen when there are disputes between developer and authority. Let us review the matter step by step and see what it could mean for you in the long run.

» Nature of the Issue
– You sold your ancestral shop in 2022 for Rs 85 lakh.
– You invested the full amount into a flat purchase.
– Possession and Occupancy Certificate (OC) are already given.
– Stamp duty has also been paid.
– Registration is pending due to conflict between developer and authority.

» Ownership Position Now
– Legally, until registration is done, ownership is not complete.
– You have possession but not registered title in your name.
– This creates risk if disputes or litigations arise later.
– In future, sale of property without registration may be difficult.

» Long-Term Legal Repercussions
– Without registration, loan against property will not be possible.
– If authority cancels or alters approval, you may face litigation.
– Resale value in the future may be reduced or blocked.
– Government records will not reflect you as legal owner.
– You may face complications in transferring the property to heirs.

» Taxation Aspect
– Since you invested sale proceeds of shop into flat, you aimed for capital gain exemption.
– Under income tax rules, exemption is valid only if new property is registered in your name.
– If registration is delayed indefinitely, tax authorities may question exemption claim.
– This can create liability of capital gains tax plus penalty.

» Financial Risks
– Your large capital is locked in an asset with incomplete legal status.
– If developer’s case worsens, asset value may be frozen.
– If delay prolongs, you may be unable to liquidate in emergency.
– This reduces your financial flexibility.

» Possible Way Forward
– Keep complete documentation ready: agreement to sell, payment proofs, possession letter, OC, stamp duty paid.
– Consult a real estate lawyer for local authority status.
– Push developer through association of buyers; collective pressure often works.
– File a representation before RERA or consumer forum if delay continues.
– Maintain communication with income tax advisor on exemption claim.
– If issue is likely to persist, explore legal remedies to safeguard your title.

» Practical Safeguards
– Keep record of all communication with builder and authority.
– Pay property tax in your name if possible, it helps your claim later.
– Do not delay action, as legal disputes get harder over time.
– Stay united with other buyers to share legal costs and pressure.

» Finally
You have taken a step with genuine intent by investing sale proceeds in a house. But pending registration creates long-term risks for legal ownership, taxation, and liquidity. The property may still be safe, but without registered title, you remain exposed. Immediate legal consultation and proactive follow-up with developer and authority are critical. Acting now can prevent larger complications later.

Best Regards,

K. Ramalingam, MBA, CFP,

Chief Financial Planner,

www.holisticinvestment.in

https://www.youtube.com/@HolisticInvestment

..Read more

Ramalingam

Ramalingam Kalirajan  |10872 Answers  |Ask -

Mutual Funds, Financial Planning Expert - Answered on Nov 13, 2025

Money
Dear Sir I have invested in a 2 BHK apartment in Mumbai Malad East area near Dindoshi court. The builder is GSA Grandeur. The builder promised to handover the flat possession ready to stay in December 2004. Later due to some issues he informed that the Flat shall be ready by December 2005. Now still he is saying that Falt shall be ready by August 2006. In this regard sir please advise what action I should take against the builder. The Flat cost is 1.11 CR plus registration charges from which I have paid him 1 CR. Kindly guide whom to approach for further action. Regards
Ans: You have taken a major financial step by booking an apartment. I appreciate your initiative in seeking advice. As a Certified Financial Planner, here is a structured menu of action you can take — from validating your rights to escalating with the proper authorities. Make sure to review all your documents and decisions with a qualified property lawyer before proceeding further.

» Confirm the agreement details

Check your Agreement for Sale (or Contract) and note the promised possession date: you mention December 2004, then December 2005, and now August 2006.

Verify whether the builder (GSA Grandeur) / promoter has a registered project under MahaRERA (Real Estate Regulatory Authority, Maharashtra).

See whether the project is listed on the MahaRERA website with a registration number.

Check if the builder has issued written communications about delay and extensions (emails/letters) and whether they have acknowledged the original date and the subsequent revised date.

Retain all payment receipts (you paid Rs 1 Cr out of total Rs 1.11 Cr + registration) and keep a record of when each payment was made and as per which schedule of installments.

» Understand your legal rights under the law

Under the Real Estate (Regulation & Development) Act, 2016 (RERA) and corresponding Maharashtra rules, if a promoter delays handing over possession beyond the agreed time, you have a right to compensation or withdrawal (refund) as per Section 18 of the Act.

You may ask the builder to pay interest on the amount you have paid so far for the period of delay. The model agreement under Maharashtra RERA states that if the promoter is unable to deliver within the time-schedule, the promoter should pay interest for every month of delay.

If the builder fails to deliver within a “reasonable” extended time (or fails entirely), you can choose to withdraw and seek refund of your money, along with compensation.

If the project is not registered with RERA (even though it should have been), then you may have additional grounds for legal action under consumer law or contract law.

Please note: recent judgments highlight that the builder’s delay gives you rights; but home-loan interest you paid may not be fully refundable via consumer forum as per recent rulings.

» Immediate practical steps you should take

Write & send a formal letter (by registered post) to the builder (GSA Grandeur) stating:

You booked the 2 BHK apartment in Malad East near Dindoshi Court.

The agreed (original) possession date was December 2004 (as per the agreement) and subsequent revised dates.

You have paid Rs 1 Cr out of total Rs 1.11 Cr + registration charges.

You demand the builder to clearly state the revised firm date of handing over possession, or alternatively offer you the option to withdraw and refund the money if they cannot meet a firm date.

You seek interest on the amounts paid for the period of delay, as per model agreement and RERA provisions.

Keep all your communication in writing and copy all relevant documents: payment receipts, agreement, letters from builder, any announcements, etc.

Check whether the builder has applied for or received Occupancy Certificate (OC) or Completion Certificate for the project/phase. Without OC the handover is legally incomplete.

» Approach the regulatory and legal forums

Check on the MahaRERA website whether the project is registered and find the project registration number.

If registered, you can file a complaint with MahaRERA (Maharashtra Real Estate Regulatory Authority) under the Act. As per FAQs, you may approach them for a refund, compensation and interest for delay.

If the project is not registered or the builder is non-compliant, you may also consider filing a suit in the consumer forum or appropriate civil court/contract tribunal for breach of contract.

Before filing, consult a lawyer specialising in real estate/consumer law so that all your evidence and claims are framed properly.

» Evaluate your options: continue vs withdraw

If the builder now gives you a firm handover date (with OC, all works completed) then you may choose to continue, given that you have already invested a large sum.

However, if the builder is still giving vague dates (August 2006 or beyond) and there are no signs of progress (OC pending, works incomplete), then you should seriously consider withdrawal and refund.

In that event, you must ask for: full refund of amount paid, interest for delay period (and compensation if justified), plus possible damages for alternative accommodation/rent you may have taken.

Monitor whether the builder is proceeding with construction, obtaining approvals, and has conveyed clear timelines.

» Assessing risk & safeguarding yourself

Since you made the payment long ago and the possession is delayed significantly, there is time-value and risk involved.

Make sure your title rights are secure: the agreement must clearly state your unit, floor, parking (if any), and your payments.

Avoid making any further significant payments unless you receive a possession letter and builder gives you the keys and OC/occupancy certificate.

Check for any lien, mortgage or charge on the builder’s property which may delay transfer further.

Note that property/real estate is subject to large delays and builder insolvency risk; hence your proactive action is wise.

» Document checklist for your case

Agreement for Sale (signed by you and builder) with possession date clause.

Payment receipts/Cheque copies of your payments (1 Cr paid) and records of registration charges.

Written communications from builder about revised dates (December 2005, August 2006).

Project registration certificate on MahaRERA (if available).

Status of Occupancy Certificate / Completion Certificate for the building.

Construction status photographs, society formation records, if any.

Correspondence showing builder’s acknowledgment of delay or your demand for possession/refund.

Any rent/alternative accommodation expense you incurred due to delay (if applicable).

» Timeline of action

Immediately send the registered letter to builder demanding firm date or refund.

Within 1-2 months if builder does not respond with firm date, file complaint with MahaRERA or initiate legal action.

Keep monitoring builder’s progress; if there is substantial delay (many years beyond promised date) your case will become stronger.

Maintain all documents and remain proactive; deadlines and records matter in these matters.

» Final Insights
You have a strong basis to assert your rights. The fact that possession was promised years ago and is still delayed means you are well within your rights to demand either speedy handover or refund/compensation. Initiate formal written demand, verify builder registration under MahaRERA, maintain all records, and seek regulatory/legal redress if builder remains non-responsive. With the right approach and evidence, you can compel the builder to perform or compensate you. Your prompt action now will protect your investment and avoid further loss.

Best Regards,

K. Ramalingam, MBA, CFP,
Chief Financial Planner,
Holistic Investment Planners
www.holisticinvestment.in

https://www.youtube.com/@HolisticInvestment

..Read more

Latest Questions
Ramalingam

Ramalingam Kalirajan  |10872 Answers  |Ask -

Mutual Funds, Financial Planning Expert - Answered on Dec 06, 2025

Asked by Anonymous - Dec 06, 2025Hindi
Money
Dear Sir/Ma'am, I need some guidance and advice for continuing my mutual fund investments. I am a 36 year old male, married, no kids yet and no debts/liabilities as such. I have couple of savings in PPF, NPS, Emergency funds and long term investing in direct stocks. I recently started below mentioned SIPs for long term to grow wealth. Request you to review the same and let me know if I should continue with the SIPs or need to rationalize. Kindly also advice on how to invest a lumpsum amount of around 6lacs. invesco small cap 2000 motilal oswal midcap 2700 parag parikh flexicap 3000 HDFC flexicap 3100 ICICI prudential largecap 3100 HDFC large and midcap 3100 HDFC gold etf FOF 2000 ICICI Pru equity and debt fund 3000 HDFC balanced advantage fund 3000 nippon india silver etf FOF 2000
Ans: You already built a solid foundation. Many investors delay planning. But you started early at 36. That gives you a strong advantage. You have no liabilities. You have long term thinking. You also have diversified savings like PPF, NPS, Emergency funds and direct stocks. That shows clarity and discipline. This approach builds wealth with less stress over time.

You also started systematic investments in equity funds. That is a positive step. Your selection covers multiple categories like large cap, mid cap, small cap, flexi cap, hybrid and precious metals. So the intent is right. You are trying to create a broad portfolio. That gives balance.

» Your Portfolio Composition Understanding
Your current SIP list includes:

Small cap

Mid cap

Flexi cap

Large cap

Large and mid cap

Hybrid category

Gold and Silver FoF

Equity and Debt allocation fund

Dynamic hybrid fund

This shows you are trying to cover many segments. But too many categories can create overlap. When there is overlap, you get confusion during review. It also makes portfolio discipline difficult. You may think you are diversified. But the holdings inside may repeat. That reduces efficiency.

Your portfolio now looks like:

Equity dominant

Hybrid for stability

Metals for hedge

So the broad direction is fine. But simplifying helps in long-term habit building.

» Fund Category Duplication
You hold:

Two flexi cap funds

One large and mid cap fund

One pure large cap fund

One mid cap fund

One small cap fund

Flexi cap funds already invest across large, mid, small. Then large and mid also overlaps. So the large cap exposure gets repeated. That may not add extra benefit. But it increases monitoring complexity.

So I suggest rationalising. Keep one fund per category in core. Keep satellite space for only high conviction.

» Core and Satellite Strategy
A structured portfolio follows core and satellite method.

Core portfolio should be:

Simple

Long term

Stable

Satellite portfolio can be:

High growth

Concentrated

Based on your thinking level, you can structure like this:

Core funds:

One large cap

One flexi cap

One hybrid equity and debt fund

One balanced advantage type fund

Satellite funds:

One mid cap

One small cap

One metal allocation if needed

This division gives clarity. You can continue SIPs with review every year. No need to stop and restart often. That reduces behavioural mistakes.

» Your Current SIP List Review with Suggested Streamlining

You can consider continuing:

One flexi cap

One large cap

One mid cap

One small cap

One balanced advantage

One equity and debt hybrid

You may reconsider keeping both flexi caps and both gold silver funds. One of each category is enough. Because too many funds do not increase returns. It complicates tracking.

Precious metal funds should not be more than 5 to 7 percent in your portfolio. This is because metals are hedge assets. They do not create compounding like equity. They act as protection during cycles. So keep them small.

» How to Use the Rs 6 Lakh Lump Sum
You asked about lump sum investing. This is important. Lump sum should not go fully into equity at one time. Markets move in cycles. So use a staggered method. You can invest the lump sum through STP (Systematic Transfer Plan). You can keep the amount in a liquid fund and set STP toward your chosen growth funds over 6 to 12 months.

This reduces timing risk. It also creates discipline. So your Rs 6 lakh can be deployed gradually. You may use 50% towards core equity funds and 30% toward satellite growth category. The remaining 20% can go into hybrid category. This gives balance and comfort.

» Regular Funds Over Direct Funds
One important point many investors miss. Direct funds look cheaper. But they demand deep knowledge, discipline, and behaviour control. Most investors lose more through emotional selling and wrong timing than they save on expense ratio.

With regular funds through a Mutual Fund Distributor with Certified Financial Planner qualification, you get guidance, structure and correction. The advisory discipline protects you during market extremes. That is more valuable than a small saving in expense ratio.

A personalised planner also tracks portfolio drift, rebalancing need and category shifts. So regular fund investing gives long-term benefit and behaviour coaching.

» Actively Managed Funds over Index or ETF
Some investors choose index funds or ETF thinking they are simple and cheap. But they ignore drawbacks.

Index funds or ETF will not avoid weak companies in the index. They will invest whether the company grows or struggles. There is no fund manager decision making. So when markets are at peak, index funds continue aggressive exposure. In downturns also they fall fully. There is no cushion.

Actively managed funds work with research teams. They can avoid bad sectors. They can shift allocation based on market and economy. Over long term, this gives better alpha and stability. So continuing with actively managed funds creates better wealth compounding.

» SIP Continuation Strategy
Once the rationalisation is done, continue SIPs every month without interruption. Pause and restart behaviour damages compounding power. SIP works best when you go through all market cycles. You benefit more during corrections because cost averaging works.

So continue SIP amount. You can also review SIP increase every year based on income. Increasing SIP by 10 to 15 percent every year helps you reach large corpus faster.

» Asset Allocation Based Approach
One key point in wealth creation is having the right asset mix. Equity gives growth. Hybrid gives balance. Metals give hedge. Debt gives safety. Your asset allocation should stay aligned to your risk profile and time horizon.

Since you are young and have long term horizon, higher equity allocation is fine. But as time moves, rebalancing is important. Rebalancing protects gains and restores allocation.

So review your asset allocation every year or during major life events like child birth, home buying or retirement planning.

» Behaviour Management
Many portfolios fail not due to bad funds. They fail due to bad decisions. Selling during correction. Stopping SIP when market falls. Chasing past return performance. These mistakes reduce wealth.

Your discipline so far is good. Continue to stay patient during volatility. Equity rewards patience and time.

» Financial Goals Clarity
Since you have no children now, you can decide your long-term goals. Typical goals may include:

Retirement

Future child education

Dream lifestyle purchase

Health care reserves

When goals are clear, investment purpose becomes stronger. So you can map each fund category to goal horizon. Short-term goals should not use equity. Long-term goals should use equity with hybrid support.

» Role of Review and Monitoring
Review once in a year is enough. Frequent review can create anxiety. Annual review helps check:

Fund performance

Expense drift

Category relevance

Allocation balance

Then adjust only if needed. This progress helps you stay confident and aligned.

» Taxation Awareness
Equity mutual funds taxation rules are:

Short term (below one year holding) taxable at 20 percent

Long term (above one year holding) gains above Rs 1.25 lakh taxable at 12.5 percent

Debt mutual funds are taxed as per your income slab.

So always hold equity funds for long term. That reduces tax impact and gives better growth.

» SIP Increase Plan
You can create a simple plan to increase SIP over time. For example:

Increase SIP at every salary increment

Increase SIP during bonus time

Use rewards or extra income for investing

This habit accelerates wealth. So by the time you reach 45 to 50 years, your investments could reach a strong level.

» Insurance and Protection
Before investing large, ensure you have term insurance and health insurance. If not already done, it is important. Insurance protects wealth. Without insurance, even a small medical event can impact investment plan. So review this part also. Since you are married, cover both.

» Wealth Behaviour Mindset
You are already disciplined. Just keep these simple principles:

Invest without stopping

Review once a year

Avoid funds overlap

Follow asset allocation

Avoid reacting to media noise

This helps you reach long term milestones.

» Finally
You are on the right track. Only fine tuning and simplification is needed. Your discipline is visible. Your portfolio will grow well with structure, patience and periodic review. Use the Rs 6 lakh with STP approach. And continue SIP with rationalised categories.

With time and consistency, wealth creation becomes effortless and peaceful. You just need to stay committed and avoid overthinking during market movements.

Best Regards,
K. Ramalingam, MBA, CFP,

Chief Financial Planner,

www.holisticinvestment.in

https://www.youtube.com/@HolisticInvestment

...Read more

Dr Dipankar

Dr Dipankar Dutta  |1837 Answers  |Ask -

Tech Careers and Skill Development Expert - Answered on Dec 05, 2025

Career
Dear Sir, I did my BTech from a normal engineering college not very famous. The teaching was not great and hence i did not study well. I tried my best to learn coding including all the technologies like html,css,javascript,react js,dba,php because i wanted to be a web developer But nothing seem to enter my head except html and css. I don't understand a language which has more complexities. Is it because of my lack of experience or not devoting enough time. I am not sure. I did many courses online and tried to do diplomas also abroad which i passed somehow. I recently joined android development course because i like apps but the teaching was so fast that i could not memorize anything. There was no time to even take notes down. During the course i did assignments and understood the code because i have to pass but after the course is over i tend to forget everything. I attempted a lot of interviews. Some of them i even got but could not perform well so they let me go. Now due to the AI booming and job markets in a bad shape i am re-thinking whether to keep studying or whether its just time waste. Since 3 years i am doing labour type of jobs which does not yield anything to me for survival and to pay my expenses. I have the quest to learn everything but as soon as i sit in front of the computer i listen to music or read something else. What should i do to stay more focused? What should i do to make myself believe confident. Is there still scope of IT in todays world? Kindly advise.
Ans: Your story does not show failure.
It shows persistence, effort, and desire to improve.

Most people give up.
You didn’t.
That means you will succeed — but with the right method, not the old one.

...Read more

DISCLAIMER: The content of this post by the expert is the personal view of the rediffGURU. Investment in securities market are subject to market risks. Read all the related document carefully before investing. The securities quoted are for illustration only and are not recommendatory. Users are advised to pursue the information provided by the rediffGURU only as a source of information and as a point of reference and to rely on their own judgement when making a decision. RediffGURUS is an intermediary as per India's Information Technology Act.

Close  

You haven't logged in yet. To ask a question, Please Log in below
Login

A verification OTP will be sent to this
Mobile Number / Email

Enter OTP
A 6 digit code has been sent to

Resend OTP in120seconds

Dear User, You have not registered yet. Please register by filling the fields below to get expert answers from our Gurus
Sign up

By signing up, you agree to our
Terms & Conditions and Privacy Policy

Already have an account?

Enter OTP
A 6 digit code has been sent to Mobile

Resend OTP in120seconds

x